Job scheduling method and system

Assignee: Hitachi Ltd
•
Filing: 1987-07-17
•
Granted: 1989-07-25
•
Expires: 2007-07-17
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A job scheduling method for scheduling of job allocation to various resources, wherein each workload of a job is allocated to each time unit along a time axis in units of job and resource type. Based on the workload allocated in units of resource type, an initial workload for all resources at each time unit is calculated. A first workload balancing is performed for an initial workload at a time unit exceeding a resource capacity so as to balance the initial workload within the resource capacity. Thereafter, a second workload balancing is performed so as to balance a workload allocated in units of resource type within its resource capacity.

Inventors

  • 👤 Isao Tsushima
  • 👤 Norihisa Komoda
  • 👤 Masao Yagi
  • 👤 Tetsuo Kusuzaki

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-23 16:52
CPC Classifications
G; G06; G06Q; G06Q10/00; G06Q10/06; G05; G05B; G05B19/00; G05B19/02; G05B19/418; G05B19/41865; G06Q10/063; G06Q10/0631; G06Q10/06311; G06Q10/063116; G06Q10/06312; Y; Y02; Y02P; Y02P90/00; Y02P90/02

Claims Analysis

Total Claims: 8
Claim 1
Independent Claim 155 words
A job scheduling method for scheduling of job allocation to various resources comprising the steps of: inputting data associated with jobs and resources; allocating a workload of each job to each time unit along a time axis in units of job; allocating said workload to said each time unit in units of resource type; calculating an initial workload for all resources at said each time unit, in accordance with said workload allocated in units of resource type; performing a first workload balancing for a time unit whose initial workload for all resources exceeds a resource capacity, so as to make the workload at said time unit within said resource capacity; after said first workload balancing, performing a second workload balancing so as to make the workload allocated in units of resource type within its resource capacity; and outputting, as a job schedule, each workload at said each time unit obtained by said second workload balancing.
Claim 2
Dependent Claim 155 words
A job scheduling method for scheduling of job allocation to various resources comprising the steps of: inputting data associated with jobs and resources; allocating a workload of each job to each time unit along a time axis in units of job; allocating said workload to said each time unit in units of resource type; calculating an initial workload for all resources at said each time unit, in accordance with said workload allocated in units of resource type; performing a first workload balancing for a time unit whose initial workload for all resources exceeds a resource capacity, so as to make the workload at said time unit within said resource capacity; after said first workload balancing, performing a second workload balancing so as to make the workload allocated in units of resource type within its resource capacity; and outputting, as a job schedule, each workload at said each time unit obtained by said second workload balancing.
Claim 3
Dependent Claim 37 words
A job scheduling method according to claim 1, wherein said first workload balancing step includes a step of performing at least one of right-shift, left-shift and cutting processings for an excessive workload at said each time unit.
Claim 4
Dependent Claim 32 words
A job scheduling method according to claim 1, wherein said second workload balancing step includes a step of performing a relieving function for relieving a processing by one resource to another resource.
Claim 5
Dependent Claim 166 words
A job scheduling system for scheduling of job allocation to various resources comprising: means for inputting data associated with jobs and resources; means for allocating a workload of each job to each time unit along a time axis in units of job; means for allocating said workload to said each time unit in units of resource type; means for calculating an initial workload for all resources at said each time unit, in accordance with said workload allocated in units of resource type; means for performing a first workload balancing for a time unit whose initial workload for all resources exceeds a resource capacity, so as to make the workload at said time unit within said resource capacity; means for, after said first workload balancing, performing a second workload balancing so as to make the workload allocated in units of resource type within its resource capacity; and means for outputting, as a job schedule, each workload at said each time unit obtained by said second workload balancing.
Claim 6
Dependent Claim 166 words
A job scheduling system for scheduling of job allocation to various resources comprising: means for inputting data associated with jobs and resources; means for allocating a workload of each job to each time unit along a time axis in units of job; means for allocating said workload to said each time unit in units of resource type; means for calculating an initial workload for all resources at said each time unit, in accordance with said workload allocated in units of resource type; means for performing a first workload balancing for a time unit whose initial workload for all resources exceeds a resource capacity, so as to make the workload at said time unit within said resource capacity; means for, after said first workload balancing, performing a second workload balancing so as to make the workload allocated in units of resource type within its resource capacity; and means for outputting, as a job schedule, each workload at said each time unit obtained by said second workload balancing.
Claim 7
Dependent Claim 37 words
The job scheduling system according to claim 4, wherein said means for performing the first workload balancing includes at least one of right-shift, left-shift and cutting processing means for an excessive workload at said each time unit.
Claim 8
Dependent Claim 30 words
The job scheduling system according to claim 4, wherein said means for performing the second workload balancing includes relieving means for relieving a processing by one resource to another resource.

References Cited (Backward Citations)

US3643227A Cited
US3648253A Cited
US3662401A Cited
US3703725A Cited
GB1339090A Cited
US4183083A Cited
GB1452865A Cited
US4383298A Cited
US4580207A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1992-07-24 1993-01-23 1993-07-25 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1996-07-24 1997-01-23 1997-07-25 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2000-07-24 2001-01-23 2001-07-25 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag